### **1. Duct Assembly**
- **Short ducts** can be assembled entirely on the ground.
- **Longer ducts** should be segmented (each segment ≤10m) to ensure proper alignment and avoid twisting or deformation.
- **Flange connection**:
- Use gaskets to ensure a tight seal.
- Bolts should be evenly tightened, with nuts facing the same direction.
### **2. Duct Positioning (Installation)**
- **Check supports**: Verify levelness, elevation, and stability before installation.
- **Small/low ducts**: Manual lifting with simple scaffolding.
- **Large/long ducts**: Use hoists, pulleys, or ropes for lifting. A common method is suspending ducts from scaffolding before placing them on supports.
- **Installation sequence**: Main ducts first, then branches and vertical ducts.
### **3. Alignment & Fixing**
- Adjust ducts to ensure **horizontal/vertical alignment** before final fixing.
- Follow design specifications for secure fastening.
### **Key Safety & Quality Considerations**
- **Flexible connectors** (e.g., canvas or synthetic leather) must be used between ducts and fans (min. 200mm length).
- **Sloped installation** for condensation-prone ducts, with drainage at low points.
- **Explosion-proof ducts** require grounding at flange joints.
- **High-altitude work** (>4m) mandates safety harnesses and secure scaffolding.
This process is widely referenced in Chinese standards (e.g., **GB50243-2016**) and aligns with global HVAC installation practices. For detailed regulations, refer to local codes or .
Would you like additional details on specific steps (e.g., flange sealing, fire damper installation)?
Contact: FOSHAN IDEAI MACHINERY CO,LTD
Phone: 86-18934379910
E-mail: machineryideal@gmail.com
Whatsapp:86-18934379910
Add: Room 3336,third floor, No.101-102, huangqi Guangfo roadside lot , Dali Town , Nanhai District , Foshan City
We chat